Description
When Grenfell resident Ed Daffarn first heard about the multimillion pound refurbishment of the tower, he welcomed it. The estate had, in his view, become increasingly run down in recent years.
But as the refurbishment progressed, he says residents felt their voices weren’t heard. Meanwhile architects and contractors selected materials which would burn easily in a fire.
Kate looks at how cost-cutting and a race to the bottom in the construction industry had devastating consequences for the refurbishment of Grenfell Tower.
Presenter: Kate Lamble
Producer: Josephine Casserly
Production coordinator: Janet Staples
Audio engineers: James Beard and Gareth Jones
Story consultant: Simon Maybin
Editor: Penny Murphy
The Inquiry’s Phase 2 report was released this week, distilling 400 days of evidence and more than three hundred thousand documents. The report concluded the fire which killed 72 people was the culmination of “decades of failure” by government and others in the construction industry. It set out a...
Published 09/06/24
In the early hours of the 14th of June 2017, a fire broke out in a tower block in West London. This fire was both a personal tragedy and a national scandal.
It began in Flat 16 of Grenfell Tower. Before long, the flames reached combustible cladding and insulation, which had been installed on the...
Published 09/06/24